Thursday, October 21, 2010

Amazing Construction 10

Building a Global Icon

Excavation work began for Burj Khalifa in January 2004 and over the ensuing years to its completion, the building passed many important milestones on its goal to become the tallest man-made structure the world has ever seen. In just 1,325 days since excavation work started in January, 2004, Burj Khalifa became the tallest free-standing structure in the world.


Burj Khalifa Construction Timeline

January 2004

Excavation started

February 2004

Piling started

March 2005

Superstructure started

June 2006

Level 50 reached

January 2007

Level 100 reached

March 2007

Level 110 reached

April 2007

Level 120 reached

May 2007

Level 130 reached

July 2007

Level 141 reached - world's tallest building

September 2007

Level 150 reached - world's tallest free-standing structure

April 2008

Level 160 reached - world's tallest man-made structure

January 2009

Completion of spire - Burj Khalifa tops out

September 2009

Exterior cladding competed

January 2010

Official launch ceremony

Construction Highlights

Over 45,000 m3 (58,900 cu yd) of concrete, weighing more than 110,000 tonnes were used to construct the concrete and steel foundation, which features 192 piles buried more than 50 m (164 ft) deep. Burj Khalifa's construction will have used 330,000 m3 (431,600 cu yd) of concrete and 39,000 tonnes (43,000 ST; 38,000 LT) of steel rebar, and construction will have taken 22 million man-hours.


Exterior cladding of Burj Khalifa began in May 2007 and was completed in September 2009. The vast project involved more than 380 skilled engineers and on-site technicians. At the initial stage of installation, the team progressed at the rate of about 20 to 30 panels per day and eventually achieved as many as 175 panels per day.


The tower accomplished a world record for the highest installation of an aluminium and glass façade, at a height of 512 metres. The total weight of aluminium used on Burj Khalifa is equivalent to that of five A380 aircraft and the total length of stainless steel bull nose fins is 293 times the height of Eiffel Tower in Paris.


In November, 2007, the highest reinforced concrete corewalls were pumped using 80 MPa concrete from ground level; a vertical height of 601 metres. Smashing the previous pumping record on a building of 470m on the Taipei 101; the world’s second tallest tower and the previous world record for vertical pumping of 532 metres for an extension to the Riva del Garda Hydroelectric Power Plant in 1994. The concrete pressure during pumping to this level was nearly 200 bars.


The amount of rebar used for the tower is 31,400 metric tons - laid end to end this would extend over a quarter of the way around the world


At over 828 metres (2,716.5 feet) and more than 160 stories, Burj Khalifa holds the following records:

• Tallest building in the world

• Tallest free-standing structure in the world

• Highest number of stories in the world

• Highest occupied floor in the world

• Highest outdoor observation deck in the world

• Elevator with the longest travel distance in the world

• Tallest service elevator in the world


Tallest of the Supertall

Not only is Burj Khalifa the world’s tallest building, it has also broken two other impressive records: tallest structure, previously held by the KVLY-TV mast in Blanchard, North Dakota, and tallest free-standing structure, previously held by Toronto’s CN Tower. The Chicago-based Council on Tall Buildings and Urban Habitat (CTBUH) has established 3 criteria to determine what makes a tall building tall. Burj Khalifa wins by far in all three categories.


Height to architectural top

Height is measured from the level of the lowest, significant, open-air, pedestrian entrance to the architectural top of the building. This includes spires, but does not include antennae, signage, flagpoles or other functional-technical equipment. This measurement is the most widely used and is used to define the Council on Tall Buildings and Urban Habitat rankings of the Tallest Buildings in the World.


Highest occupied floor

Height is measured from the level of the lowest, significant, open-air, pedestrian entrance to the highest continually occupied floor within the building. Maintenance areas are not included.


Height to tip

Height is measured from the level of the lowest, significant, open-air, pedestrian entrance to the highest point of the building, irrespective of material or function of the highest element. This includes antennae, flagpoles, signage and other functional-technical equipment

http://www.burjkhalifa.ae/language/en-us/home.aspx

No comments: